KUALA LUMPUR (Nov 19): Shin Yang Group Bhd (KL:SYGROUP) is taking over the completion of two delayed offshore patrol vessels (OPVs) for the Malaysian Maritime Enforcement Agency (MMEA), securing a RM316 million contract to complete a troubled naval procurement project originally awarded to THHE Destini Sdn Bhd.
The group's wholly-owned subsidiary, Shin Yang Shipyard Sdn Bhd, will undertake the remaining works on OPV 2 and OPV 3 as the rescue contractor, according to a Bursa Malaysia filing on Thursday.
The contract, excluding sales tax, is worth RM129.56 million for OPV 2 and RM186.44 million for OPV 3. The project runs from Oct 15, 2026 to Oct 14, 2029, with OPV 2 scheduled for completion within 36 months and OPV 3 within 30 months.
The three-vessel programme was initially awarded to THHE Destini for RM740 million in 2017, with delivery originally scheduled for August 2020.
In 2018, TH Heavy Engineering Bhd (THHE), which held a 49% stake in THHE Destini, became part of Urusharta Jamaah Sdn Bhd (UJSB), a special purpose vehicle established by Minister of Finance Inc to restructure the pilgrim fund's investments after it faced financial difficulties. By the end of 2021, THHE acquired the remaining stake in THHE Destini, making it a wholly-owned subsidiary.
In June 2022, UJSB set up an oversight committee to monitor the project, citing its national importance. The government injected RM44 million and UJSB RM120 million to complete the first vessel, KM Tun Fatimah, which was delivered in January 2024.
However, delays continued on the remaining two vessels. THHE Destini's contract was terminated on Dec 31, 2024, with Home Minister Datuk Seri Saifuddin Nasution Ismail announcing the decision in February 2025. THHE Destini was also subjected to liquidated ascertained damages exceeding RM12 million for delays in delivering OPV 2 and OPV 3.
The government subsequently approved an additional RM200 million to complete the remaining vessels, on top of the RM120 million left from the original allocation.
Shin Yang Group first disclosed its proposed appointment on May 27, 2025, after receiving a letter of intent from the Home Ministry dated May 20. The letter was not legally binding, with the final award subject to negotiations on pricing, payment terms and other conditions.
Under the latest contract, Shin Yang Group will complete two vessels designed for extended border patrols, exclusive economic zone surveillance and search-and-rescue operations.
Each vessel measures 83 metres in length and 13.7 metres in width, with a displacement of at least 1,600 tonnes. They are designed to reach speeds of at least 20 knots and have a mission endurance of 21 days. Their specifications include a 30mm remotely controlled weapons station.
Acceptance of the contract is subject to an irrevocable performance bond of RM5.27 million. It also requires participation in the government's Professional Training and Education for Growing Entrepreneurs-Ready to Work programme and compliance with its Industrial Collaboration Programme requirements.
Shin Yang Group shares closed unchanged at 71 sen on Thursday, valuing the group at RM852 million.
Read also:
Cost to complete two delayed maritime agency patrol vessels estimated at RM319.6 mil — minister
Govt approves additional RM200 mil to complete two delayed patrol vessels for maritime agency
Shin Yang Group gets letter of intent from home ministry to build two patrol vessels for maritime agency
Cover Story 2: ‘We are concentrating on our mission’
Cover Story: The 30 biggest stocks sold to UJSB and how they are doing now