KUALA LUMPUR (July 15): The cost of completing two out of three offshore patrol vessels (OPVs) for the Malaysian Maritime Enforcement Agency (MMEA) is now estimated at RM319.6 million.
Home Minister Datuk Seri Saifuddin Nasution Ismail said the Ministry of Home Affairs (KDN) will enter into price negotiations with the company to be appointed for the completion works, in line with a letter issued by the Ministry of Finance (MOF) on June 5, 2026.
“The completion works for the remaining two vessels, OPV 2 and OPV 3, are currently pending the appointment of a company to undertake the completion contract,” he said in a written parliamentary reply on Tuesday (July 14).
Saifuddin was responding to Tanah Merah member of Parliament Datuk Seri Ikmal Hisham Abdul Aziz, who had asked for the latest status of the construction of the remaining two Tun Fatimah-class OPVs, which have been stalled for a prolonged period.
Saifuddin said KDN is also in discussions with the liquidator to gain access to the Pulau Indah shipyard, where the remaining construction works are expected to take place.
The ministry expects work on OPV 2 and OPV 3 to resume as early as November 2026, subject to the activation of the Pulau Indah shipyard.
The OPV project has been closely watched due to repeated delays, changes in contractors and rising costs involving the construction of MMEA’s maritime enforcement vessels.
To date, MMEA has only received one of the three vessels, OPV 1, which was named KM Tun Fatimah and handed over to the agency on Jan 2, 2024.
The original contract to supply, deliver, test and commission three OPVs, complete with fittings and accessories, was awarded to THHE Destini Sdn Bhd for RM740 million, with delivery scheduled within 42 months by August 2020.
However, the project encountered delays, prompting the MOF to take over the project from THHE Destini in January 2023 after identifying several issues, including the need for a RM152.6 million government loan to complete and deliver the first vessel.
THHE Destini was initially 51% owned by Destini Bhd (KL:DESTINI) and 49% owned by TH Heavy Engineering Bhd. TH Heavy Engineering later acquired Destini’s stake for RM121.13 million in late 2021, making THHE Destini a wholly owned subsidiary.
Saifuddin later confirmed that THHE Destini’s contract was terminated through a mutual termination agreement on Dec 31, 2024, with the decision announced in February 2025. The company was also slapped with liquidated ascertained damages exceeding RM12 million for delays in delivering OPV 2 and OPV 3.
Following the termination, the government approved an additional RM200 million to complete the remaining two vessels, bringing the total cost of the three OPVs to RM940 million.
In May 2025, Shin Yang Group Bhd’s (KL:SYGROUP) unit Shin Yang Shipyard received a letter of intent (LOI) from KDN to undertake the completion works for OPV 2 and OPV 3. However, the LOI is not legally binding and no formal contract has been signed to date.