KUALA LUMPUR (Nov 27): Malakoff Corp Bhd (KL:MALAKOF) said it expects earnings to improve in the fourth quarter following the full resumption of a coal-fired power generation unit at subsidiary Tanjung Bin Power Sdn Bhd (TBP) in Pontian, Johor.
For the third quarter ended Sept 30, 2026 (3QFY2026), net profit fell 1.61% to RM27.76 million from RM28.21 million a year earlier, mainly due to the lower contribution from TBP following a steam turbine generator rotor failure, as well as the reversal of a net realisable value provision for coal inventories recognised in 3QFY2025.
The decline was partly offset by higher contributions from associates, the group said in its bourse filing on Friday.
Quarterly revenue, however, climbed 33.82% to RM2.26 billion from RM1.69 billion, driven by higher energy payments from TBP and Tanjung Bin Energy Sdn Bhd amid rising applicable coal prices, as well as increased payments from Segari Energy Ventures Sdn Bhd following a higher despatch factor.
No dividend was declared for the quarter.
For the nine months ended Sept 30, Malakoff’s net profit declined 36.35% to RM79.58 million from RM125.03 million a year earlier, while revenue fell 3.35% to RM5.55 billion from RM5.74 billion.
Malakoff said TBP had returned to full generating capacity following Unit 30’s resumption of base-load operations on Aug 9, after the successful installation of its rotor.
“While the earlier disruption of the plant is still reflected in this quarter’s profit, we are heading into the final quarter of the year in a stronger position,” group CEO Syahrunizam Samsudin said in a statement.
He said Malaysia’s electricity demand continued to rise amid industrial expansion and digitalisation, highlighting the need for reliable generation capacity.
Malakoff’s GB3 plant in Lumut, Perak, also resumed commercial operations in October, adding 429MW ahead of schedule, while its Prai power plant in Penang has been operating since April.
Both plants’ extended operations leverage existing infrastructure, Syahrunizam said.
The group’s hydropower portfolio is also set to expand after the Sustainable Energy Development Authority approved higher capacity and improved feed-in tariff rates for its three hydropower plants in Kelantan, lifting their combined installed capacity to 95.67MW.
On the recent incident involving the coal conveyor belt system at its Tanjung Bin Complex in Kukup, Johor, Syahrunizam said the group’s two coal-fired power plants, with a combined generation capacity of 3,100MW, continued to operate without disruption and were supported by sufficient coal inventory. Remedial works are expected to be completed by the end of November, he added.
Malakoff shares closed one sen or 1.32% higher at 77 sen on Friday, valuing the group at RM3.83 billion.