KUALA LUMPUR (Nov 23): Kinergy Advancement Bhd (KL:KINERGY) is set to become the sole contractor responsible for developing and operating captive power plants to supply electricity to data centres and other energy-intensive industries at industrial sites owned by Matrix Concepts Holdings Bhd (KL:MATRIX).
The two companies have entered into a binding exclusive term sheet, under which Kinergy will be exclusively appointed as the engineering, procurement, construction and commissioning (EPCC) contractor, as well as the operations and maintenance (O&M) provider, for the proposed captive power plants.
Matrix Concepts will provide the land for the developments and undertake site preparation, infrastructure provision, stakeholder coordination and planning approvals, according to Kinergy's bourse filing on Monday.
Kinergy, meanwhile, will be responsible for feasibility studies, regulatory approvals, licensing, construction and subsequent operations of the power plants.
The proposed facilities are intended to provide dedicated electricity supply to industrial developments catering to data centres, semiconductor manufacturing, advanced manufacturing and other power-intensive operations.
However, the companies did not disclose the estimated investment value, generation capacity, number of power plants or development timeline under the arrangement.
Definitive agreements arising from the binding term sheet would be announced in due course, Kinergy said.
Its executive deputy chairman and group managing director Datuk Dr Lai Keng Onn said captive power plants could help industrial developments reduce their exposure to grid supply constraints and disruptions by providing dedicated on-site electricity generation.
"While grid connectivity remains fundamental, large-scale industrial developments and energy-intensive sites require a more comprehensive approach to power planning, particularly in ensuring sufficient and reliable electricity to support future tenant requirements and long-term operations," he said in a separate statement.
"By bringing generation closer to the point of consumption, this approach can help mitigate exposure to grid supply constraints and interruptions, while providing greater certainty over electricity availability and continuity," Lai added.
Kinergy said the arrangement would expand its involvement in power generation and utility infrastructure beyond conventional electrical construction.
The group has been involved in several power generation projects, including as Petroliam Nasional Bhd's (PETRONAS) local technical partner for the 72MW Sipitang power plant and the main EPCC contractor for the 120MW Labuan power plant.
It has also secured electrical works for a hyperscale data centre as part of its expansion into energy-intensive infrastructure.
Matrix Concepts' industrial development portfolio includes the 1,100-acre Sendayan TechValley in Negeri Sembilan, which has been fully developed, and the ongoing 1,000-acre MVV TechValley within the Malaysia Vision Valley 2.0 development corridor.
The property developer is also expanding its industrial footprint, having announced plans for an RM8 billion industrial and logistics park at MVV TechValley in partnership with Golog Holdings last year, alongside a proposed RM2.1 billion industrial-led mixed development in Kulai, Johor.
However, Kinergy did not specify which of Matrix Concepts' industrial sites would be involved in the proposed captive power plant developments.
Shares in Kinergy slipped 0.5 sen or 1.35% to 36.5 sen as of Monday's noon market break, giving the group a market capitalisation of RM797.55 million, while Matrix Concepts dropped one sen or 1.11% to 89 sen, valuing the property developer at RM1.67 billion.