KUALA LUMPUR (Nov 2): Econpile Holdings Bhd’s (KL:ECONBHD) subsidiary has secured a RM73 million contract to carry out piling and foundation works for a new hospital building at Hospital Tung Shin in Kuala Lumpur.
The contract, awarded by SA Architects Sdn Bhd on behalf of Hospital Tung Shin, covers earth-retaining structures, piling, pile caps and the lowest basement slab.
The project involves demolishing existing structures and constructing a new hospital building with multiple levels of hospital facilities, car parks, offices and basement levels.
The project is expected to be completed within 21 months.
The contract is its second contract win for the financial year 2027. It won a RM24.4 mil piling job for a 53-storey apartment along Jalan Tun Razak in October.
Econpile’s shares were up 4% to 13 sen a share, valuing the company at RM184.28 million. Year to date the stock is down 43%.