The Sabah portion of the Pan Borneo Highway (PBH) will go down in the Malaysian record books as one of the costliest road infrastructure projects in the region.
When Phase 1 of the PBH for Sabah was mooted in 2015, the cost was estimated at RM12.9 billion. The latest government disclosure says the cost has ballooned to RM24.9 billion.
This means that the cost for the entire 706km stretch of Phase 1 is slightly more than RM35 million per kilometre. With the project yet to be completed, the final cost is almost certain to rise further.
Phase 1 is divided into 1A and 1B, comprising 35 work packages. According to the latest Auditor General’s report, only four of these packages had been completed as at end-March this year while nine of the remaining work packages were classified as problematic (Projek Sakit).
A Projek Sakit classification means that the contractor is unable to complete the job, which will have to be put out to tender again.
The surge in the project cost has been attributed to a rise in land acquisition expenditure and a shift back to the conventional contracting model in 2019 following a change in the federal government. This resulted in the Ministry of Works taking over the job from a project delivery partner. The project is now being managed by the Public Works Department of Sabah.
But beyond the land acquisition and change in project management, what other reasons are there for the cost escalation?
For instance, were the contractors who were awarded the work packages able to deliver within the stipulated cost and time? And why were the big names in the construction sector that are known for their strong execution excluded from the project?