
This article first appeared in The Edge Malaysia Weekly on July 13, 2026 - July 19, 2026
PENINSULAR Malaysia’s latest competitive bidding exercise for combined cycle gas turbine (CCGT) power plants — the second in two years — saw five submissions at its close on July 1, sources tell The Edge.
The Energy Commission requested for proposals with the aim of seeing new plants start operations between 2029 and 2031 as part of a repowering exercise as old plants are retired and electricity demand continues to grow strongly, driven by rising electrification and the influx of data centre projects (see sidebar).
Notable players in the picture include a consortium involving YTL Power International Bhd (KL:YTLPOWR) with 750mw planned in Pulau Indah, Klang and a joint venture (JV) between Petroliam Nasional Bhd (PETRONAS) and Edra Power Holdings Sdn Bhd (700mw), two sources say.
It is understood that utility giant Tenaga Nasional Bhd (KL:TENAGA) has also submitted a bid for a 700mw gas plant project in Connaught Bridge, Klang. The location was home to one of the oldest power plants in the country with an 800mw-capacity plant, which has since been decommissioned. The location currently houses a smaller, 375mw power plant that will operate until 2037.
According to a source, Genting Bhd (KL:GENTING), through its power unit, has also submitted a 1,400mw proposal in Gebeng, Pahang.
This latest bidding round, dubbed NEWGEN26, comes on the heels of an earlier bidding exercise in 2025 (NEWGEN25) that saw a Tenaga JV with Aurora Power Generation Sdn Bhd being the sole winner of new project awards with 1,400mw capacity in Terengganu under a 15-year power purchase agreement (PPA).
Under the 2025 exercise, the Energy Commission also awarded a PPA extension to three companies for their existing plants, namely Tenaga (1,262mw), Malakoff Corp Bhd (KL:MALAKOF) (2,082mw) and Edra Power (1,375mw) to end-2029 and early 2030. PETRONAS, meanwhile, secured a 150mw additional capacity for its power plant in Pengerang, Johor.
The bidding exercise doubles as the new direction for Malaysia’s gas power plant industry. Bidders have to show their ability to secure gas turbines — currently at a bottleneck — and natural gas supplies and ideally suitable land with easy connectivity to the national power grid and gas pipeline.
According to a consultation paper published by the Energy Commission, Peninsular Malaysia could see as much as 7,848mw of new gas power plant capacity between 2029 and 2031.
In the same period, as much as 6,930mw worth of coal and gas-fired power plant capacity could retire, according to data on the website of the Grid System Operator, an entity responsible for the operation of the national grid, including the scheduling and dispatch of generating units.
The bulk of the plant retirement would come from coal, comprising the nearly 1,475mw Sultan Aziz Power Station in Kapar, which is 60:40-owned by Tenaga and Malakoff (retiring in July 2029); the 2,070mw Janamanjung plant in Perak, owned by Tenaga (August 2030); and the 2,100mw Tanjung Bin power plant that is 90%-owned by Malakoff (September 2031).
The idea is to phase out coal and replace it with gas-fired plants as baseload and reduce emissions in line with the government’s commitment to international practices.
However, the influx of gas-fired power plant developments globally — to meet rising electrification demand while managing emissions — has resulted in a market squeeze for gas turbines, in some cases, requiring down payment of up to one-third of the turbine’s price.
It is understood that YTL Power is among the few players that have secured turbines for new bids. Malakoff, which is said to be close to securing two 1,400mw power plants, previously announced it had secured four turbines from Mitsubishi Power Ltd. Tenaga, which has the NEWGEN25 1,400mw tender win in Terengganu and another 1,400mw project in the state, said a month ago that it had signed an agreement for six gas turbines, also from Mitsubishi Power, with up to 4,200mw capacity.
However, the lead time remains tight for new projects. According to Wood Mackenzie, gas turbine manufacturing backlogs have stretched power plant lead times to as long as five years, compared to 3½ years previously.
It said in a report, “Hot-section component manufacturing — particularly single-crystal blade production — remains the industry’s critical bottleneck, as these precision processes can only be performed at scale by a handful of global suppliers”, even when key manufacturers like GE Vernova Inc, Mitsubishi Power’s parent Mitsubishi Heavy Industries Ltd and Siemens Energy AG had confirmed manufacturing capacity expansion plans.
Save by subscribing to us for your print and/or digital copy.
P/S: The Edge is also available on Apple's App Store and Android's Google Play.