KUALA LUMPUR (May 14): Tenaga Nasional Bhd or TNB (KL:TENAGA) and Malakoff Corp Bhd (KL:MALAKOF) are expected to benefit most from Malaysia’s first power plant tender in over 10 years, as demand rises sharply due to data centres.
Malaysia hasn't had a power plant award since 2016, but TNB has already signed 5.9 gigawatt (GW) in power deals with data centre operators, with demand projected to grow 5% a year.
The last one was a direct award in August 2016 — a 1.2GW gas facility in Pulau Indah, Klang — which started operating in the first quarter of 2025. There hasn't been a power plant tender for more than 10 years.
The Energy Commission recently launched a request for proposal (RFP) for new baseload capacity — the minimum amount of electricity that must be constantly supplied to meet everyday demand. It includes two categories:
TNB and Malakoff are front runners for Category 1, as both have about 2GW of gas-fired capacity with expiring power purchase agreements. Edra Power, with 1GW capacity, is also a contender, according to CGS International in a note on Wednesday.
For Category 2, likely participants include TNB, Malakoff, YTL Power International Bhd (KL:YTLPOWR), and Edra, due to their strong track records and financial strength, said CGS. Petronas Gas Bhd (KL:PETGAS) may also join, as it plans to expand its power business.
With about 9GW of existing capacity set to expire by 2030 and limited new projects, Malaysia could face a 5GW shortfall. Nevertheless, CGS maintained its 'overweight' view on the utilities sector, calling the RFP a key growth opportunity under the National Energy Transition Roadmap.
At the time of writing on Wednesday, TNB shares were down four sen or 0.28% at RM14.30, with a market capitalisation of RM83.36 billion. Malakoff was half a sen or 0.60% lower at 83.5 sen, with a market cap of RM4.18 billion.