KUALA LUMPUR (Dec 4): Deputy Defence Minister Adly Zahari said on Thursday that the overall progress of the long-delayed littoral combat ships (LCS) project had reached 70.1% as of Oct 25 this year.
The progress — which includes design, construction, equipping, and testing — is slightly behind schedule by 0.59%, as the planned progress was 70.69%, according to the contract’s timeline.
On the first LCS (LCS 1), the construction is in its final phase and is expected to be completed by the end of this year, Adly noted.
The ship will then undergo harbour acceptance tests (HATs) and sea acceptance trials (SATs), conducted by the Royal Malaysian Navy over the next two years.
“As for the second LCS (LCS 2), it will be launched into the water by mid-2025, before undergoing HAT and SAT,” Adly said during the oral question-and-answer session in Parliament on Wednesday.
He was responding to a question from Datuk Seri Ikmal Hisham Abdul Aziz (Perikatan Nasional-Tanah Merah) about the projected timeline for the operational testing of LCS 1, and the estimated launch date for LCS 2.
Adly reaffirmed that the Defence Ministry is closely monitoring the construction progress of the LCS. This includes conducting regular site inspections, and holding meetings with the contractor Lumut Naval Shipyard Sdn Bhd (LNS) on a monthly, or even weekly basis.
The LCS project has been under scrutiny in recent years, due to significant delays and cost overruns. Initially budgeted at RM6 billion, the project’s costs escalated to RM9.18 billion, and eventually reached RM11.22 billion.
The scope of the project was also reduced from six vessels to five, with revised delivery dates for the ships set for August 2026, April 2027, December 2027, August 2028, and April 2029, respectively.
For more Parliament stories, click here.