KUALA LUMPUR (March 12): The Energy Commission has announced the list of 30 shortlisted bidders of the Large Scale Solar @ MEnTARI (LSS4), totalling 823.06MW out of the offered 1,000MW.
This comprises 20 bidders covering 323.06MW under Package P1 at between 10MW and below 30MW, as well as 10 bidders across 500MW under Package P2 between 30MW and 50MW.
The shortlisted bids for Package 1 ranged between 18.5 sen/kWh and 24.81 sen/kWh. Meanwhile for Package 2, the bids ranged between 17.68 sen/kWh and 19.7 sen/kWh.
Among the identified listed companies that have been awarded the projects are:
The commissioning of the project will be in late 2022 or early 2023. The shortlisted companies are required to fulfil certain requirements which will be issued by the Energy Commission in due time.