This article first appeared in Forum, The Edge Malaysia Weekly on March 8, 2021 - March 14, 2021
The Littoral Combat Ship (LCS) programme is now at a difficult crossroads. The programme was slated to see its first delivery in April 2019, with the remaining ships being delivered every six months after that.
It is now March 2021, nearly two years since the original due date, and it would appear that no end is in sight for the troubled procurement project. As at December last year, the minister of defence had confirmed that while RM6 billion had been paid out, the first ship of the class was only 59.79% complete.
Even more worrying is the way the government has framed the solution to the problem. Currently, two options are being mooted — either to terminate the project with the current contractor, Boustead Naval Shipyard (BNS), or to continue it with the current contractor. It was announced that the government would not consider selecting Naval Group (previously known as DCNS), BNS’ joint venture partner in the project and owner of the intellectual property of the LCS, as a rescue contractor.
No additional money will be injected into the programme but rather, the government will only use the remaining RM3 billion of funds left to complete a minimum of two ships, a position which it considers realistic. The ceiling value for the project is around RM9 billion, of which RM6 billion has already been spent. Of the RM6 billion already spent, allegedly RM1 billion is unaccounted for.
This framing of the problem itself is fundamentally flawed for several reasons. The government’s position reflects solely the bureaucratic and fiduciarily responsible position to take, which is to prevent further loss of value to the government. While this imperative is not wrong by itself, it fails to account for the primary purpose of the procurement project — to give the Royal Malaysian Navy (RMN) much-needed modern and streamlined naval fighting capability. Whether the government cancels the project, or only completes it with two ships accepted, it has failed to adequately answer the risks of either decision to achieve combat effectiveness of the RMN, in a time when maritime security is increasingly being tested.
Bear in mind that the vast majority of RMN’s ships are well over 25 years old. The whole reason the RMN embarked on its 15-to-5 programme was to replace ageing platforms considered no longer economically viable and obsolete. If the LCS project fails, it behooves us to ponder what the government will do to offset the shortfall in capabilities.
In the larger context of defence procurement, the government also has to rethink the current long-term thinking as well. The five-year Malaysia Plans may not be an entirely suitable way to frame defence asset procurements given that most of the ships have service lives that stretch well beyond five years.
The proposed solutions also ignore another fundamental fact — that the supplier of the ships, BNS, as a subsidiary of Boustead Heavy Industries Corp, which in turn is a subsidiary of Boustead Holdings and thereby the Armed Forces Fund Board (LTAT), is a de facto agency of the government too. By turning a blind eye to BNS’ interests in the matter, the government in effect would be allowing the sole entity capable of carrying out maintenance and repair procedures for RMN and other maritime security agencies to fail.
As it currently stands, BNS’ financial position leaves much to be desired, and is a drag on Boustead Holdings as a whole. Reportedly, this has stemmed from a variety of factors, chiefly the need to service old loans from a previous abortive project, and lower cash inflows from reduced maintenance contracts. Without a more comprehensive rescue plan, regardless of a project continuation or cancellation, questions will inevitably arise as to BNS’ longevity as a going concern. If this is allowed to happen, the consequences would not only be felt by RMN, but also BNS’ parent companies, namely Boustead and LTAT. LTAT’s performance in the preceding years has left much to be desired as it is.
Secondly, the decision to exclude BNS’ French joint venture partner, Naval Group, from being a part of the solution also needs serious rethinking. While the government’s intentions are noble, in that it wishes to build domestic design skills for the industry, it also needs to account for the fact that contractually, BNS must still answer to Naval Group for any design changes it makes. Naval Group is the design authority of the Gowind-class frigate and has the final say on its detailed design documentation.
The detailed design of the ship remains the major obstacle to its completion. It is essentially a blueprint that tells shipbuilders how to fit the ship’s various electronic equipment and fixtures to the ship’s hull. Without it, all of the ship’s fittings currently sitting in storage cannot be physically installed into the body of the ship. Given the pressing need to complete the project soon, the government must consider an arrangement that more actively involves the design authority in order to expedite the completion of the detailed design, failing which delays will continue indefinitely.
To be clear, the LCS as a component of 15-to-5 is very much needed to fulfil the RMN’s requirements for a naval surface combatant capable of anti-surface, anti-submarine and air defence missions at sea. However, this did not prevent the acquisition from being mired in political interference that has compromised its integrity.
BNS was given the letter of award for the project on Dec 16, 2011 and signed the contract on July 17, 2014, yet discussion of the 15-to-5 strategic plan really only picked up in public discourse around 2015, with the document being officially published in 2018. This indicates an ex-post rather than ex-ante justification for its procurement. Questions thus arise as to whether the design selected was based on its merits as opposed to lobbying by vendors.
Questions also arise as to the integrity of the project’s funding. On Feb 11, 2020, former defence minister Mohamad Sabu, his deputy Liew Chin Tong and auditor-general Tan Sri Ambrin Buang met with the prime minister to present the latest findings of the investigation into the project. Ambrin found that about RM1 billion of project funds were unaccounted for.
Current senior minister for security and minister of defence Datuk Seri Ismail Sabri stated in December that an investigation by the Malaysian Anti-Corruption Commission is underway, and so too is a forensic audit. We can only hope that the government will take these investigations to their logical conclusion. Those who have acted irresponsibly must be taken to task; monies embezzled must be returned and then used to pay for the proper project expenses.
Yet, the spectre of corruption still looms in this affair. Beyond just holding people accountable, every effort must be made by the government to prevent history from repeating itself. It is good that the defence minister has announced that BNS’ management and project team will have to be restructured in the event that the government decides to continue with the project. But beyond that, the government must also reflect on its own errors in the endeavour.
In the larger context of things, there must be a change to the way the defence industry and procurement is conducted. The White Paper has outlined the need not only for a clear commitment of investment in defence acquisition but also a defence industry policy that is clear and sets clear rules of the road.
If future projects are to be successful, the lessons learnt from this episode need to be incorporated into these reforms, lest we repeat the errors of the past. We can only hope that the forthcoming defence investment plans and defence industrial policy will adequately address these concerns when they are released and debated in parliament in the next two years.
Nik Mohamed Rashid Nik Zurin is a researcher at Research for Social Advancement (REFSA), a think-tank promoting social advancement in Malaysia. Liew Chin Tong is chairman of REFSA and the former deputy minister of defence.
Save by subscribing to us for your print and/or digital copy.
P/S: The Edge is also available on Apple's App Store and Android's Google Play.