CHINA General Nuclear Power Corp (CGN), the investment holding company which controls power plant operator Edra Power Holdings Sdn Bhd, is understood to be claiming RM170.33 million from 1Malaysia Development Bhd (1MDB) and the Malaysian government.
The amount sought is for unpaid income and value added tax, and other claims in Bangladesh, Egypt and Denmark, the documents viewed by The Edge indicate.
Correspondence between the parties, which is centred on a notice of claim by CGN against 1MDB, PM Global Energy Bhd (a unit of 1MDB) and the Ministry of Finance, suggests that talks are ongoing. Whether there will be an amicable solution or whether the claims will be contested remains to be seen.
CGN did not respond to questions from The Edge.
In a nutshell, CGN’s claims involve income tax liabilities of RM49.94 million and value added tax liabilities of RM90.67 million in Bangladesh, plus withholding tax amounting to RM1.63 million in Denmark and tax liabilities of RM28.09 million in Egypt.
According to the documents dated mid-February this year, CGN in giving the background to the claims explains that pursuant to a sale and purchase agreement (SPA), 1MDB and its subsidiaries agreed to sell all their energy assets to Edra Power Holdings, in a deal sealed on March 23, 2016.
“Pursuant to the SPA (in 2016), the vendors are liable to indemnify the purchaser for certain liabilities arising prior to the signing of the SPA in respect of the energy assets acquired by the purchaser,” CGN says.
The Chinese outfit goes on to say that it had sent a notice of claim in end-January to 1MDB but had not received any response.
In another document sighted by The Edge, Edra Power Holdings president and executive director Zhong Xianjue sought for the claim to be paid by Feb 10.
Edra Power Holdings is the unit that houses the power assets bought from 1MDB.
It is not known for certain why 1MDB has not settled the claim and whether the claim is valid.
A director of 1MDB and PM Global Energy, Mohd Hishyamuddin Awang Abu Bakar, in response to another letter in mid-February says: “We are still in the midst of reviewing the contents of your letter and notice. We will respond as soon as possible.”
Late last year, news reports revealed that a number of ports in the country were facing issues with the scanners used to check cargo.
The Royal Malaysian Customs were said to be having problems with 13 X-ray scanners acquired from CGN Begood Technology Co Ltd, which is also a unit of CGN, at a cost of RM242.24 million.
CGN Begood is understood to have won the tender to supply the scanners in January 2020, and installation commenced in September 2021, but the performance of the scanners was said to be unsatisfactory with a scanning ability of only 53%.
A Port of Tanjung Pelepas report had it that only 1,093 images were recorded after 2,053 scans.
On top of that, there has been friction between CGN and the local parties.
When CGN acquired 1MDB’s power assets, it marked the first time in Malaysian history that power plants were sold to a foreign company in entirety.
According to the regulations, foreign shareholding in power plants was to be capped at 49%. A listing of Edra Power Holdings, which would have resulted in CGN paring down its stake, was in the pipeline but it never happened.
Instead of an IPO, CGN sold 37% of Edra Power Holdings to another Chinese outfit, China Southern Power Grid International. It is not clear if the expectation was for CGN to divest some shares to a Malaysian company.
To recap, in a 16-month buying spree between March 2012 and July 2013, 1MDB paid more than RM12 billion cash for power generation assets. The government-linked investment fund took over power plants from tycoon Tatparanandam Ananda Krishnan for RM8.5 billion as well as from Genting Bhd for RM2.3 billion. 1MDB also bought a 75% stake in Jimah Energy Ventures Holdings for RM1.23 billion.
With these acquisitions, 1MDB owned 11 power plants in Malaysia, Egypt, Bangladesh, Pakistan and Abu Dhabi with gross installed capacity under management of 5,702.5MW and an effective capacity of 4,748.5MW.
1MDB’s initial plan was to undertake an IPO to list its power generation unit to raise fresh funds. However, things didn’t pan out as planned.
As it was cash-strapped, 1MDB decided to hive off its power assets, instead of undertaking a listing exercise. In November, it found a keen buyer from China, namely CGN group, a state-owned entity, willing to pay RM9.83 billion in cash for the power assets.
The more than RM9 billion in cash proceeds was timely as it allowed 1MDB to meet its debt payment obligations then.
In addition, 1MDB found another Chinese state-owned firm China Railway Engineering Corp (M) Sdn Bhd (CREC) to partner with Iskandar Waterfront Holdings Bhd to buy a 60% stake in Bandar Malaysia Development, located at the former Royal Malaysian Air Force base in Sungai Besi in the southern part of Kuala Lumpur, for over RM7 billion.
The real estate development project, however, did not take off under three governments. It was terminated in July last year.
Edra Power Holdings’ profit after tax (PAT) shrunk substantially to RM23.31 million on the back of RM4.47 billion in sales for the financial year ended Dec 31, 2020 (FY2020), compared with PAT of RM554.12 million from RM6.02 billion in revenue the year before. It is not clear what transpired in 2020.
It is also noteworthy that between 2016 and 2020, Edra Power Holdings paid out more than RM1.65 billion in dividends.
While the claim of RM170.33 million may not be much in the bigger scheme of things, it could drive a wedge in the relationship between the two which, according to sources, is already frayed.